Other Information

The following is historical information about NSTAR's electric system and key milestones.

  • NSTAR's Highest Historical Peak Load: 4,978 MW (July 22, 2011)
  • 3% Private Net Metering Cap: 149.34 MW (3% of highest historical peak load)
  • 3% Public Net Metering Cap: 149.34 MW (3% of highest historical peak load)

Net Metering Totals as of July 7, 2014:

3% Private Net Metering Cap (149.34 MW cap):

  • Projects Online: 59.74 MW
  • Projects with Applications Submitted: Visit massaca.org.

3% "Public" Net Metering Cap (149.34 MW cap):

  • Projects Online: 64.92 MW
  • Projects with Applications Submitted: Visit massaca.org.